No | Item | Duration | PENCAPAIAN | Remark | |
Unit 1 | Unit 2 | ||||
1 | Drying out refractory | 10 days | 07 – 16 September 2017 | 09 – 18 November 2017 | DONE (Unit #1 & #2) |
2 | Chemical cleaning Boiler | 4 days | 30 September – 4 October 2017 | 23 -26 December 2017 | DONE (Unit #1 & #2) |
3 | First firing Boiler | 1 day | 06 November 2017 | 04 January 2018 | DONE (Unit #1 & #2) |
4 | Steam blow | 6 days | 18 December – 23 December 2017 | 06 -11 Jan 2018 | DONE (Unit #1 & #2) |
5 | Unit start up (Rolling Turbine & Generator) | 2 days | 27 December – 28 December 2017 | 14 – 15 January 2018 | No Load Test (3000 Rpm) DONE (Unit #1 & #2) |
6 | Stringing Transmission line finish | 85 days | 29 November 2017 – 18 Februari 2018 | DONE (Line #1 & #2) | |
7 | Inspection Test T/L by PLN Pusertif | 4 days | 20 Februari – 23 Februari 2018 | DONE (Line #1 & #2) | |
8 | Final Inspection T/L by PLN Pusertif | 2 days | 26 Maret 2018 – 27 Maret 2018 | DONE (Line 1 & 2) | |
9 | RLB Transmisson Line | 0 days | 14 May 2018 | Done (Line 1 & 2) | |
10 | Commissioning Gardu Induk Finish | 0 days | 14 May 2018 | Done (Line 1 & 2) | |
11 | RLB Subtation & Transformer | 0 days | 15 May 2018 | Done (Line 1 & 2) | |
12 | Energizing 150 kV Supply | 0 days | 18 May 2018 | 19 May 2018 | Done (Line 1 & 2) |
13 | Rekomendasi laik Sinkron (RLS) | 0 days | 26 May 2018 | 26 July 2018 | Done (Line 1 & 2) |
14 | First Syncron | 0 days | 26 May 2018 | 26 July 2018 | Done (Line 1 & 2) |
15 | Load Rejection (50%, 75% & 100%) | 5 days | 03-07 Juni 2018 | 27-31 July 2018 | DONE (Unit #1 & #2) |
16 | Realibilty Run | 3 days | 10 – 12 July 2018 | 01 – 03 August 2018 | DONE (Unit #1 & #2) |
17 | NDC Test | 4 days | 13 – 17 July 2018 | 05- 08 August 2018 | DONE (Unit #1 & #2) |
18 | SLO | 0 days | 01 August 2018 | 15 August 2018 | DONE (Unit #1 & #2) |
19 | COD | 0 days | 02 August 2018 | 31 August 2018 |