Pencapaian

No Item Duration PENCAPAIAN Remark
Unit 1 Unit 2
1 Drying out refractory 10 days 07 – 16 September 2017 09 – 18 November 2017 DONE (Unit #1 & #2)
2 Chemical cleaning Boiler 4 days 30 September – 4 October 2017 23 -26 December 2017 DONE (Unit #1 & #2)
3 First firing Boiler 1 day 06 November 2017 04 January 2018 DONE (Unit #1 & #2)
4 Steam blow 6 days 18 December – 23 December 2017 06 -11 Jan 2018 DONE (Unit #1 & #2)
5 Unit start up (Rolling Turbine & Generator) 2 days 27 December – 28 December 2017 14 – 15 January 2018 No Load Test (3000 Rpm)
DONE (Unit #1 & #2)
6 Stringing Transmission line finish 85 days 29 November 2017 – 18 Februari 2018 DONE (Line #1 & #2)
7 Inspection Test T/L by PLN Pusertif 4 days 20 Februari – 23 Februari 2018 DONE (Line #1 & #2)
8 Final Inspection T/L by PLN Pusertif 2 days 26 Maret 2018 – 27 Maret 2018 DONE (Line 1 & 2)
9 RLB Transmisson Line 0 days 14 May 2018 Done (Line 1 & 2)
10 Commissioning Gardu Induk Finish 0 days 14 May 2018 Done (Line 1 & 2)
11 RLB Subtation & Transformer 0 days 15 May 2018 Done (Line 1 & 2)
12 Energizing 150 kV Supply 0 days 18 May 2018 19 May 2018 Done (Line 1 & 2)
13 Rekomendasi laik Sinkron (RLS) 0 days 26 May 2018 26 July 2018 Done (Line 1 & 2)
14 First Syncron 0 days 26 May 2018 26 July 2018 Done (Line 1 & 2)
15 Load Rejection (50%, 75% & 100%) 5 days 03-07 Juni 2018 27-31 July 2018 DONE (Unit #1 & #2)
16 Realibilty Run 3 days 10 – 12 July 2018 01 – 03 August 2018 DONE (Unit #1 & #2)
17 NDC Test 4 days 13 – 17 July 2018 05- 08 August 2018 DONE (Unit #1 & #2)
18 SLO 0 days 01 August 2018 15 August 2018 DONE (Unit #1 & #2)
19 COD 0 days 02 August 2018 31 August 2018